Chemin Goodview, Sudbury

Mise à jour du project

Avis de travaux- Le 23 juillet 2024

Réhabilitation de l’asphalte et resurfaçage

The City of Greater Sudbury will be completing road improvements on Goodview Road between M.T.C and C.K.S.O Roads in Sudbury.

Construction by the City’s Contractor, GIP Interpaving Limited will begin August, 2024 and is expected to be completed by October 2024. 

Work will typically take place during daylight hours Monday to Friday. Weekend or night work may be required.

Gestionnaire de projet:
Andrew Peltomaki
705-690-5541


Détails des travaux:

  • Remove and replace asphalt 
  • Drainage improvements 
  • Replacement of existing road cross culverts

Échéancier du projet:

  • Avis de travaux- Le 23 juillet 2024
  • Préavis de travaux de construction- Le 28 mai 2024